Appendix O:
Extended payments
Background
Regulations 2(1), 62(A), 69(8), 76(4) and
Schedule 5A of the Housing Benefit (General) Regulations as
amended and regulations 2(1), 53A, 66(4) and Schedule 5A of the
Council Tax Benefit (General) Regulations 1992, as amended,
provide for EPs of HB and CTB to be made.
Findings
The HB and CTB EP scheme was introduced on
1 April 1996 as part of a package of measures designed to
encourage the long-term unemployed to return to work. The aim of
the scheme is to help with housing and CT costs during the
transition from IS or Income-Based Jobseekers Allowance
(JSA(IB)) to the receipt of first wages. LAs must have systems in
place to enable EPs to be processed urgently.
To be eligible for an EP, a claimant must
satisfy all the following conditions:
- IS or JSA(IB) must have lasted for a
continuous period of 26 weeks because the claimant was:
- actively seeking work
- receiving IS or JSA(IB) as a lone
parent or carer
- on a government training course
- IS or JSA(IB) has ceased because the
claimant (or any partner) has either:
- started work
- increased their hours worked
- increased their wages
- the new job, hours or earnings are
expected to last at least 5 weeks
- there is a continuing liability for
rent and/or CT for the period of EP
- the claimant is under 60 years of age
when IS ceases or, in JSA(IB) cases, under 60 for a woman
or under 65 for a man
- the claim is made in the method and
time prescribed.
A claim for EP must be made on a form
NHB1-EP or equivalent and completed forms should be returned to a
jobcentre, BA office or LA office within 8 days of the date IS or
JSA(IB) stopped. The claim must be made by the person in receipt
of IS or JSA(IB). BA must certify claims received to show that
the claimant has satisfied the 26-week qualifying condition
before the claim is forwarded to the LA for processing.
LAs should have procedures in place to
identify claims for EPs and any subsequent in-work claims for HB
or CTB and should fast track them as appropriate. There are
subsidy incentives and penalties to encourage LAs to deal with
in-work claims quickly. If the claimant has already made a claim
for an EP, an LA may earn an additional £10 subsidy if it
determines an in-work claim:
- within 14 days of the date the in-work
claim is made
- within 14 days of the date the claim
for EP is made
- within 7 days of the date when all the
relevant information is received
whichever of these is the latest. In
addition the LA must determine the in-work claim during the
4-week EP period.
The timing for making a claim for EP is
crucial, as any claim received after the 8-day period is not
eligible for payment and cannot be backdated. It is essential
that the receiving office date stamps the claim form to ensure
that the 8-day period can be correctly assessed. Claimants who
believe either BA or ES staff have given them wrong advice can
request compensation payments from BA. LAs were advised of the
compensation scheme in Circular HB/CTB A4/97 and are expected to
advise claimants if appropriate.
Thanets approach to EPs
Our inspection found that Thanet has some
good practices for processing EPs.
Thanet has a dedicated team that takes
responsibility for assessing EPs. Membership of this team rotates
on a day-to-day basis. Staff are aware of the qualifying
conditions for EPs and compensation arrangements. Priority is
given to NHB1-EP forms when received and they are immediately
forwarded to the section.
Thanet has produced a leaflet to explain
EPs. The leaflet includes information on claiming compensation
payments from BA for misleading advice. Thanet uses standard
letters that include information on the claimants right to
review if EPs are refused.
The number of claims for EPs in 1997/98
recorded by the LA was 1,530, of which 1,154 were accepted and
376 were refused. The number of fast track in-work claims was
609, of which 424 were accepted and 185 were refused. (Source:
Thanet District Council).
We selected 20 cases for examination and
our findings are shown in the following table.
| Fig.
O.1: 1997/98 EP claims awards made or not made |
| |
Number of cases
|
%
|
| Awards made |
15
|
75
|
| Awards refused |
5
|
25
|
| Total |
20
|
100
|
Source: BFI analysis
All the claims were made using the correct
claim form and BA had certified them. Claims had not been made
within the 8-day period in 2 cases and had been refused
accordingly.
| Fig.
O.2: 1997/98 EP claims processed correctly or
incorrectly |
| |
Number of cases
|
%
|
| Processed correctly |
17
|
85
|
| Processed incorrectly |
3
|
15
|
| Total |
20
|
100
|
Source: BFI analysis
From the selected cases, 3 claims were
processed incorrectly. The reasons were:
- one claim had been certified by BA
that the 26-week rule had not been met
- one claimant had stated that the work
was to last less than 5 weeks
- one claim had been made by the partner
of the person who was in receipt of JSA(IB).
The general turnaround time from ES and BA
to Thanet is 2 days. We found that 2 of the sample claims had not
been date stamped by ES or BA. In these instances, provided they
were date stamped by the LA within the 8 days, no issue of delay
would arise. However, the failure to date stamp the claim forms
by BA or ES could have been an important issue and could have
resulted in BA having to make compensation payments.
From the sample, 9 of the claims for EP
also had successful in-work claims fast tracked. Thanet qualified
for the £10 additional subsidy in all 9 cases.
Conclusions
Thanet processes claims for EPs and fast
track in-work claims promptly. The accuracy of processing could
be improved, although the errors we found do not appear to be due
to lack of knowledge about entitlement conditions.
Review rights are covered satisfactorily in
the relevant notices of determination Thanet issues.
  
|